Project - RTC Underground Communication Conduit
| Offeror Name: |
FBDC |
| Contract Number: |
0002 |
| Total Dollar Amount: |
$ 167,178.00 |
| Procurement Agency/Customer: |
Baltimore USACE |
| Title of Contract: |
RTC Communication Conduit |
| Contract Type: |
Lump Sum |
| Period of Performance: |
August 2002 – December 2002 |
Primary Customer Points of Contact:
Baltimore USACE
Jon Sadler 410-962-2616
|
|
|
|
Brief Description of the RTC Underground Communication
Conduit Project:
In August 2002, the Fort Berthold Development Corporation
was awarded the above contract, which was completed
in December 2002. The project involved design &
installation of underground conduits for future cabling
work. FBDC was under contract for a feasibility study
for the best location and route to install conduits
for a 6 mile run. Upon completion of the study, FBDC
performed the work to install the conduits and bypass
areas as not to disturb the operations of the facility.
FBDC performed underground boring to limit the disruption
to a minimum. FBDC completed the project with minimum
disturbance to the facility while saving costs to the
owner by determining the most economical route for the
conduits.
|
|
|
 |
Tribal Owned 8A with Open Task Order Construction (TOCC) Contract.
Contract # DACA31-01-D-0046
IDIQ Omaha USACE
Contract # W9128F-06-D-0029
25 Million 5 Years
National IDIQ Department of Interior
Gov Works
Contract # 0406-CT-60704
50 Million 5 Years
Small Business
Administration
|
|
|
|
|
| |